Assign Activities
Use the Activity Assignments tab to split a selected position between activities into sub-projects.
Ways to access
--
Options
Using the buttons on the right edge you can add activity, delete highlighted entries from the list and open the Properties of an activity allocation.
Models
Using this model the quantity of contract items is assigned to activities. The field rate is always related to the relevant model when entering.
Fixed - The quantity of contract items is entered as a fixed value for the Activity.
Per unit of Quantity - The quantity of contract items is calculated using the Quantity of the Activity, e.g. 1 Quantity = 1 contract item.
Percentage of quantity from contract item - The quantity of contract items is entered as a percentage for the Activity, e.g. 25% of the number of contract items.
Time-based - This model can only be used for contract items with a time unit! The quantity of contract items is calculated using the duration of the Activity, e.g. 1 hour = 1 contract item.
Performed - This flag shows whether an activity is already finished.
Example
For the contract item topsoil the quantity is allocated with 6.000 m2 for the activity remove topsoil 1 and with 2.250 m2 for the activity remove topsoil 2.
This gives a total of 8.250 m2, which equals 91,67% of the total contract item quantity.