Calculate: Quantity

The quantity of an activity is calculated using the duration and the work rate. Also see Calculate Activities.

  1. Select the activity.

  2. Select in the Details Toolbar on the tab Calculation in the field Calculate: Quantity.

  3. Select the Unit for the Quantity.

  4. Enter the Planned Work rate and select a Time unit for the rate.

The rate value corresponds to the Quantity per chosen time unit.

Example: m²/h.

  1. The Quantity is calculated by Duration * Work Rate.

Next topic: ---

Further information

Activity

Calculation