Calculate: Work Rate

The work rate of an activity is calculated using the entered quantity of work and the duration. Also see Calculate Activities.

  1. Select an activity.

  2. Select in the Details Toolbar on the tab Calculation in the field Calculate: Work rate.

  3. Enter the Quantity and select a Unit for the Quantity.

  4. Select a Time unit for the work rate.

  5. The Work rate is calculated using the Quantity / Duration.

The rate value corresponds to the work rate per chosen time unit.

Example: m²/h.

To calculate the quantity over the distance, set the value in the field Set quantity by to Activity length and enter the Quantity factor (how many units per 1 unit of distance).

Example: Along a distance of 1 meter, 4 m³ of earth is lifted. 4