Create Summary Activities
Use the Details tab to create summary activities.
Ways to access
Click the Insert Activity icon on the Insert toolbar. Then click the Details tab in the Object Properties pane.
Steps
Add a summary activity (time-distance cell)
Open a view with a time-distance cell.
On the Insert toolbar, click the Insert Activity icon (or select Insert > Object > Activity in the menu).
4. Beneath the toolbar, select a New Object Area in the Activity template list. You can always edit the activity’s visual characteristics in the Object Properties pane > Display tab later.
5. Create an activity in the time-distance cell by clicking and dragging a line/shape.
6. In the Object Properties pane > Details tab, edit the activity’s Name. Also select Summary Activity as the type on the same tab.
Create subordinate activities in a summary activity
Select an existing activity in a time-distance cell.
In the Object Properties pane > Details tab, select the Parent activity for this activity, which must be a summary activity. ...
or
Right-click an existing activity in a time-distance cell and select Activity Structure > Add activity to Summary.
In the Add Activity to Summary dialog ...
Note on linking sub-activities in a summary activity: Unlinked child activities in a summary activity keep their positions. Activities under a summary activity are not moved if they start later than the earliest possible start date for the summary activity.
Convert an activity to a summary & define its sub-activities in a bar chart
Select the activity you want to convert into a new structure.
In the Object Properties pane > Details tab, select Summary Activity as the type.
Right-click the activity you just converted and select Open Summary in Gantt Chart. A Gantt chart for the summary activity opens in a new window.
On the Insert Toolbar, click the Insert Activity icon (or select Insert > Object > Activity in the menu) to create new activities.
These new activities are automatically created as sub-activities. The distance coordinates of the new activities are set to the same values as the summary activity.To return to the time-distance cell, close the Gantt chart.