Create Haulage Activities
Use the Calculation tab to create haulage activities. An activity whose performance and planned quantity is displayed as a pale blue bar in the Mass Haulage Diagram has to be calculated when the activity is activated.
Ways to access
Create (using the Insert toolbar > Insert Activity) or select a cut or fill activity in a time-distance cell. In the Object Properties pane, click the Calculation tab.
Figure: Creating Haulage Activities
Steps
In the Calculate list, select Duration or Work rate.
In the Set quantity by list choose Selected cut area or Selected fill area.
Choose the Source and Destination in the relating fields for the haulage to be performed by the activity
Enter the Quantity (haulage).
Enter the Planned work rate.
To calculate the progress (performance) of an activity, see Analyze Progress.