Import/Export - Step 4

Use page 4 of the Import/Export Wizard to define the project scope to distinguish between projects with single and multiple sub-projects.

During import, this step is skipped if the Sub-Project-ID field is supplied within the activity attributes. In this case, the sub-project to which the activity is imported is already defined. This step is also skipped while importing library items or links.

Ways to access

Options

Multiple sub-projects can be exported or imported within one export session.

Next topic: ---