Quantity

Example of progress using quantity

The planned activity has a quantity of 10,000 m³. With regard to the Report Date, 4,000 m³ should already have been progressed. Also see Use Progress Methods.

Figure: Quantity

The real progress, however, is shown as 6,000 m³ . So in the 10 days, there was more work done than planned. The total duration has now been set to 20 days.