Allocate Resources to Activities
Use the Select Resources dialog to allocate resources to activities. When allocating resources to activities, the default settings from the library are used; these can be changed later.
Ways to access
From the Tilos Explorer, open a view with a time-distance cell. Select an activity and click the Allocations tab in the Object Properties pane. Click the Allocate (resource) icon.
Note: If the Resources tab is not visible, select Tools > Options > Functions and check the Enable resources and accounts box. …
Allocate resources to an activity
From the Tilos Explorer, open a view with a time-distance cell.
Select an activity and click the Allocations tab in the Object Properties pane. …
Note: If the Resources tab is not visible, select Tools > Options > Functions and check the Enable resources and accounts box. …
Click the Allocate (resource) icon to open the Select Resources dialog.
Select the required component resource by checking the box in the Add column.
Click OK.
In the Object Properties pane near the bottom of the screen, enter the Input value for the selected model.
Note: To use the same selection of resources for further activities, check the Keep resource selection for next use box.