Show Activity Dependencies

Use the Successors dialog to generate a list or Gantt chart view showing the whole path from the selected activity through the entire project.

Ways to access

  • Right-click an activity in a time-distance view and select Tools > Display Dependency Table in the context menu.

Options

  • Type selection - Select if you want to show the predecessor or successor path through the project.

  • Output selection - Select if you want to show the result as a list or as Gantt Chart.

Next topic: ---