Show Activity Dependencies
Use the Successors dialog to generate a list or Gantt chart view showing the whole path from the selected activity through the entire project.
Ways to access
Ways to access
Right-click an activity in a time-distance view and select Tools > Display Dependency Table in the context menu.
Options
Options
Type selection - Select if you want to show the predecessor or successor path through the project.
Output selection - Select if you want to show the result as a list or as Gantt Chart.