Assign Costs to Activities
Use the Resources tab to assign costs to activities. When allocating accounts to activities, the default settings from the library are used, but can be subsequently set individually for activities.
Ways to access
Select an activity in a view’s time-distance cell. In the Object Properties pane > Resources tab ...
Note: If the Resources tab is not visible, enable Resources and Accounts on the Tools > Options > Functions tab. ...
Allocate costs directly to an activity
Click the Add Cost icon to open the Select Account dialog.
Select the required account by checking the box next to it. The summary is listed in the lower half of the window.
Click OK to confirm.
Enter the Input value according to the relevant Model in the Details Toolbar.
Note: Should the selected account be used for further Activities, activate the option Keep account selection.