Review Floats
Use the Floats tab to see the Total Float and Free Float for a selected activity.
Ways to access
Values
Total Float
Earliest Start - The earliest possible start date of an activity, considering the logical defaults in the plan.
Earliest End - The earliest possible end date of an activity, considering the logical defaults in the plan.
Total Float - The total float is the time period in which an Activity can be pushed back without influencing critical Activities (project end). This movement does, however, influence the successors!
Free Floats
Free Start - The start date of an activity using the free float.
Free End - The end date of an activity (all free floats are taken advantage of).
Free Float - The free float is the time period in which an Activity can be pushed back, without having to move the successor.