Use the Floats tab to see the Total Float and Free Float for a selected activity.
Earliest Start - The earliest possible start date of an activity, considering the logical defaults in the plan.
Earliest End - The earliest possible end date of an activity, considering the logical defaults in the plan.
Total Float - The total float is the time period in which an Activity can be pushed back without influencing critical Activities (project end). This movement does, however, influence the successors!
Free Start - The start date of an activity using the free float.
Free End - The end date of an activity (all free floats are taken advantage of).
Free Float - The free float is the time period in which an Activity can be pushed back, without having to move the successor.