Use the Chart Definition tab to ...
Ways to access
From the Tilos Explorer, open a view, and select an existing chart object in a time or distance cell. Select the Chart Definition tab in the Object Properties pane.
Steps
Evaluate resources in a resource bar chart
From the Tilos Explorer, open a view, and select an existing chart object in a time or distance cell.
In the Object Properties pane > Chart Definition tab, add a new entry. …
Select in the Chart Type dialog - Resource bar chart. You will see the Resource Bar Chart Properties dialog.
If necessary, make new entries in the table.
Select a resource in the resource column.
If you have selected the structure of a superordinate resource, activate the option Include sub-entries.
Select an interval set for the color matching of the values. You can open the Interval Properties Dialog using the button edit Color codes.
Select the sub-project that should be evaluated for every entry in the resource plan.
Using the Tab - Display, you can define further settings for the resource plan.
Evaluate resources in a histogram
From the Tilos Explorer, open a view, and select an existing chart object in a time or distance cell.
In the Object Properties pane > Chart Definition tab, add a new entry.
Select the type - Histogram. You will see the Histogram Definition dialog.
Enter a new histogram entry in the table. You will see the Histogram Line Properties Dialog.
Select the data source: Resources.
Value: Select what you want to evaluate: Effort, Quantity, Quantity (sully) Income or Cost can be evaluated.
The planning state should be set to Current planning.
In the field Show as, select the presentation as bar or line.
If you wish to create a cumulative evaluation, activate the option Sum up.
Activate the sub project and select the relative resources for the evaluation.
Further settings for histograms can be found in the Reference Manual - Histogram.