Activity Options

Use the Activity page to define the options for Activities, for the calculation model and the display of the work rate time unit.

Ways to access

Activity

Rescheduling

If the option is not checked, the whole activity is moved. The upper Activity, it is moved to the right and the lower is moved to the left, that complete not performed Activity is beyond the report date.

If the option is checked, the upper activity, it is made longer, that complete not performed Activity is beyond the report date, the lower is made shorter.

Note: Although there is no specific function for displaying a near-critical path (like the Tools > Options > Display > for Critical path color), you can use the Ignore free floats smaller than setting that results in rescheduing in a "near-critical task".

Line Display No-Quantity (non-working line display)