Split Activities

Use the Split Activity dialog to define which method is used to split the selected activity.

Ways to access

Options (by Method)

Distance-based splits

 As from, enter the 1st splitting point and as to enter the 2nd splitting point.

Time-based splits

Additional Options can also be undertaken:

Put new activities to the same bar line: Check this option, if the Gantt chart is in non-grouped mode, both activities should appear on the same bar line.

The text at the beginning of an Activity is then only shown on the first piece and the text at the end only on the last piece.

Select the synchronization mode that should be applied.