Display User-Defined Activities

When the checkbox Customize Colors for progress is activated you can edit the line style and color of the activated Activity regarding progress.

activity > display tab > customize colors for progress (change title to dialog name)

Ways to access

Display tab options

Note: The Customize colors for progress checkbox is disabled if the selected task is in a Gantt chart view. This makes the Line display controls (Line color, Line style) unavailable.

Shape and Gantt Display

Line display

Shapes (two-dimensional activity drawings)

Lines (one-dimensional Activity-drawings)

Pressing the  button will assign the same color to not performed and performed parts of the activated Activity and to its baseline.

Next topic: ---

Further information